Classification Decision: How to create flexibility in terms of time when importing equipment to Russia

If you don’t want to declare each switch of a facility separately, the larger unit must be certified as a whole and declare it all at once. The planning effort for this is enormous; the so-called “classification decision” provides some relief.

With a so-called “classification decision”, the Federal Customs Service of Russia authorizes the import of goods in disassembled and unfinished form as well as transport across the customs territory over a certain period of time.

This means that, for example, an engine imported separately does not have to be declared as such, but is imported as part of an approved large-scale baked goods factory without having to be presented at the same time as the other parts of the facility. The entire factory is considered imported when all the components listed in the classification notice have been imported.

The most important condition for obtaining the “classification decision” is that each of the components of the overall facility is necessary for the overall system to function and it cannot be put into operation without the component! All components together are what form this entire production unit.

This classification certificate (long title: “Certificate of classification of goods transported across the customs border of the Eurasian Economic Union in an unassembled or disassembled form, including in an incomplete or unfinished form, and the import or export of which is taken over by different consignments of goods within a certain period of time”) is regulated by the Customs Code of the Eurasian Economic Union Article 21 in conjunction with Article 117 and the Russian Customs Law Nr 289 and, in addition to the possibility of partial deliveries, also provides legal certainty about the applicable customs tariff numbers and, consequently, about the import duties to be paid.

In order to receive a certificate, an application must be submitted to the Federal Customs Service, in which the entire factory and its individual components must be listed in detail. The level of detail of the listing of the components in the application, and thus also in the certificate, depends on the level of detail of the delivery (are all the nuts of the entire factory delivered separately on one truck or is an already pre-assembled conveyor system loaded on one truck).

In addition to the component or parts lists, the application must be accompanied by additional documents, such as technical descriptions, assembly plans and descriptions of the installation method, process diagrams, step-by-step descriptions of the technological process, the list of elements included in the components “fasteners”, “fastening elements”, such as screws, bolts, nuts, gaskets, clamps, connectors, fittings, flanges, etc., “accessories and tools for assembly, commissioning, testing and operation” and the like.

It should also be noted that only certain items of goods are provided for which a “classification decision” may be requested. These are mostly customs numbers 84-90, 7308, 9406.

The examination of the application is very strict and formal. Thus, the assistance of an experienced representative is highly recommended.

Deadlines:

The authority (the Federal Customs Service) has 90 days to make the decision.

The economic operator then usually has two years to import the equipment in partial shipments. After the expiration of these two years, there is a possibility to extend it 4 times for up to a year each time. So, in total, you have up to six years to import the whole manufacturing plant.

Advantages and disadvantages of the “classification decision”

The import of entire factories on the basis of this classification certificate has enormous advantages. Firstly, it is not necessary to coordinate deliveries amongst several parties and shipments can be made according to construction progress. Furthermore, the problems that often occur in transit with the required individual declaration are not to be expected.

The disadvantage of this import method is the long lead time due to the necessary planning and regulatory deadlines as well as the lack of flexibility.

At least 90 days before the first partial delivery, the application must be submitted absolutely error-free. This means that the exact part lists and the delivery units must be known long before the first delivery. If anything changes in this regard, the requirements of the classification notice can no longer be fulfilled. Very often, however, the detailed planning only takes place during the progress of the project and information relevant to the application is only available after the submission deadline.

That is why a whole facility is often-times broken down into separate sub-facilities for the purpose of better planning over multiple “classification certificates”.

[See here for an example of an application listing for classification]

 

Component No. Name of component HS-Code Quantity Unit Net weight [kg] Additional Info
1 Raw material reception:
1.1. Flour silo with vibrating bottom 7306 2 Stk.
1.1.1 Equipment for silo feeding
1.1.1.1
1.1.2 Earth connector for trucks 8536
1.1.3. Dosing screw 8428 1 Stk.
1.1.3.1 Screw tube (body) 1 Stk
1.1.3.2. Screw 1 Stk
1.1.3.3. Gear motor 1 Stk
1.1.3.4. Exhaust valve 1 Stk
1.1.4. In-line (gravity) magnet filter 1 Stk.
1.1.5. Guard rail 7326 1 Stk.
1.1.6. Mounting material, cable, switches and other accessories disassembled for transportation Stk.
1.2. Sugar silo 8479899708 1 Stk.
……
1.3. Sunflower oil storage with immersion heatert 8419899890
……
1.4.2. Stainless steel pipes 110 mm 60 lfm
2 Dough production
2.1. Vacuum pneumatic conveying system 1 Stk
2.2. Feeding station 1 Stk
2.2.1 ……….
2.3. Kneading 1 Stk
2.3.1 Power unit 1 Stk
2.3.1.1. Motor 2 Stk
2.3.1.2. Gear 2 Stk
2.3.1.3. Drivetrain 2 Stk
2.3.1.3.1 Drive shaft 4 Stk.
2.3.1.3.2 ………
2.3.1.3. Electrical cabinet 1 Stk
2.3.2 Dough tray
2.3.2.1 …..
3 Tunnel kiln 2 Stk
……….. ………………
3.4.2.3.9. Thermostat 22 Stk
…….. …………
4 Cooling and packing line
5 Automated warehouse system
………….. ……….
5.2.3.14 Conveyor belt PVC-llips 3926 2780 Stk
……… ……………. …….. …..
5.3.1. asynchronous electric motor for ventilating system 8501 24 Stk.
5.3.2 tubes for ventilating system 9 m 7306 109 Stk.
5.3.3. Lines 200 lfm
…..

Die Anträge können über das Webportal der Zollverwaltung eingebracht werden:

Similar articles

The FBL is a document of trust

With sanctions against Iran loosening, the FBL (FIATA Bill of Lading) is moving back into the spotlight. In order to deliver goods by truck to Iran, it is mandatory to…

The new Eurasian Economic Union (EAEU or EEU) Customs Code is finally due to take effect on 1 January2018 


Following a long tug-of-war, Belarusian President Lukashenko has signed the Customs Code of the Eurasian Economic Union Belarusian President Alexander Lukashenko finally agreed to and signed the EAEU Customs Code…

Roadblocks in Russia and Belarus

»This year regulations have again been adopted in Russia and Belarus that specify which roads will be blocked in the spring and from what maximum axle-load and temperature trucks are…

Efficient export controls are legally binding for exporters. These are the specifications for your company.

“At Condor, we have extensive experience in efficient export control and ICP systems, and are happy to help you develop a functional compliance program for your business.” MAG. ANDREAS GFRERER,…